Project Description

Waukomis Pumping Station Rehabilitation

Lake Waukomis, Mo.

  • Clean water pump station rehabilitation, including removal and replacement of four horizontal split-case centrifugal 300 HP pumps (two direct-drive and two variable-speed drive) with all associated mechanical piping, valves and yard piping; electrical room addition with all-new electrical equipment, controls and instrumentation; masonry restoration; roof replacement; concrete foundations; structural steel framing and aluminum grating; chain hoist; site improvements including grading, asphalt roadway and pervious concrete pavement.

  • All work was phased to allow the existing pump station to remain online for continuous operation.